Dear Member
Fire Co-ordination Statement - IPENZ PN 22
A number of members have recently been asked by various Councils
for a PN 22 Fire Co-ordination statement as part of Building
Consent application. The NZIA recommends that members do NOT sign
this statement.
This design coordination statement is provided to the Building
Consent Authority in accordance with the IPENZ Practice Note 22
Guidelines for Documenting Fire Safety Designs and is intended to
accompany the documents submitted in the application for building
consent.
When the fire designer produces documentation for the appropriate
discipline to incorporate into their building consent/construction
documents, the fire designer and other disciplines share
responsibility for correct interpretation and accurate
representation in the other disciplines' documents. Primary
responsibility for co-ordinating the design correctly rests with
the design consultant responsible for producing the
documents.
However, it is expected that the building consent documents are
referred back to the fire designer to undertake a secondary review
of the documents for compliance with the fire engineering
design.
It is also recommended in PN 22 that the Fire Safety
Designer will usually provide the Fire Co-ordination
Statement.
Kind regards
John Albert
Professional Services Manager